Current Projects

* except infrastructure projects.
* the prices in GBP should be converted in litas according to currency exchange rate of that day.

Project code

Project name

The price of the contract 

Implementation period

Project implementation

В1

Interim Spent Fuel Storage Facility (ISFSF)

194 423 296, 00 (EUR)

Start: 2005-01-12
Start of the commercial operation: 2017-05-04

 94%

В2/3/4

Solid Waste Management and Storage Facilities (SWMSF)

191 729 812,33 (EUR)

Start: 2005-11-30
Contractual completion date: 2009-11-30
Forecast completion:  2018

 90% (B2);
 87% (B3/4)

2206

 

INPP Unit 1 Turbine Hall Equipment Decontamination and Dismantling Project license documents development, Project B9/1

3 611 806 EUR
2 586 174, 78 GBP

Start: 2007-11-22
Forecast completion: 2013-11-28 (including guarantee period)

 100%

Performing dismantling works of equipment by project B9/1

implemented by INPP personnel 

 

Start: 2011-10-21
Forecast completion:
2019-06-27

 Dismantling of equipment: 100%

Decontamination works: 95%

2213 

 

INPP Unit 2 Turbine Hall Equipment Decontamination and Dismantling Project license documents development, Project B9/1(2)

implemented by INPP personnel 

Start: 2011-09-14
Completion date: 2013-10-31
Updated license for D&D received:
2014-06-18

 100%

Performing dismantling works of equipment by project B9/1(2)

implemented by INPP personnel 

 

Start: 2014-07-01
Forecast completion: 2021-04-22

Dismantling of equipment: 83%

Decontamination works: 63%

B9-2

INPP Building V1 Equipment Dismantling and Decontamination Design Development

1 710 986,58 EUR
937 291,89 GBP

Start: 2009-01-14
Completion data for the first phase: 2013-12-27
The second phase will start after 2023

 First phase 100%

2214

INPP Unit D2 equipment dismantling and decontamination

 

 

 

 2203
B9/3 (1)

 

INPP Building A1 Equipment Dismantling and Decontamination Design Development

 implemented by INPP personnel

Start: 2013-06-03

 95%

Equipment dismantling and decontamination

 

Completion: 2034 end

 4%

2207

 

Unit D1, D0 Equipment Dismantling and Decontamination Design Development

implemented by INPP personnel 

Start: 2013-06-03
Completion:
2015-09-15

 100%

 Performing dismantling works

implemented by INPP personnel 

 

Start: 2010-02-01

 99,9%

B19

Landfill Facility for Short-lived Very Low Level Waste

6 189 750,00 (EUR)

Start: 2008-05-12
B19-1 part completed in November, 2013

 100% (B19-1)
 66,9% (B19-2)

B25/1

Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste (Design)

10 492 319,00 (EUR)

Start: 2009-10-23

 97%

UP01

Project 2101. Dismantling of Units 1 Reactor Facility

Project 2102. Dismantling of Units 2 Reactor Facility*
*2102 – implementation will begin after the unloading of spent nuclear fuel from the reactor, the radiological characterization of Unit 2

-

Start: 2010-07
Forecast completion
2034-08

Percentage not measured